Roadworks and Projects   /   From November 21st 2025 at 7 h to November 22nd 2025 at 17 h

Water Main Work and Water Shutdown on Sainte-Catherine Street Between Greene Avenue and Wood Avenue


Water main work will take place on Sainte-Catherine Street, between Greene Avenue andWood Avenue, for a period of two days starting Friday, November 21.

Friday, November 21–7 a.m. to 5 p.m.

  • Excavation of two water main sections by two Constructions Morival teams to expose and prepare the pipes.

Saturday, November 22–7:30 a.m. to 5:00 p.m.

  • Water shutdown between 8 a.m. and 4 p.m. (approximate duration: 4 hours).
  • Work is expected to be completed by 5 p.m..

Updates will be provided as work progresses.